Channel Normalization in Cempaka Putih Tengah to Complete May

Central Jakarta Water Resources Sub-agency personnel are improving the water channel on both sides of Jalan Cempaka Putih Tengah III RT 01/05, Cempaka Putih Timur.

We dismantled the old channel

Cempaka Putih District's Head of Water Resources Unit, M Suhadi said the normalization of the 288 meter long channel has been carried out since March 5 by 20 Blue Troop personnel.

Karet Pasar Water Channel Upgrade Nears Early May Completion

"The work is targeted to complete by the end of May," he said, Friday (3/27).

He added that this channel normalization follows up on residents' suggestions because the surrounding area often floods when it rains, due to being unable to accommodate the water flow.

"We dismantled the old channel and replaced it using a 60 x 60 centimeter concrete u-ditch," he added.

Meanwhile, Sumadi (43), a local resident, appreciated the water channel improvement.

"Hopefully, after normalization, our residential area will no longer be flooded when it rains," he hoped.

Linked News
Popular News indeks
  1. BMKG: Sunny to Cloudy Skies Forecast Across Jakarta Today

    access_time11-09-2026 remove_red_eye1719 personDessy Suciati
  2. Pramono Urges Jakmania to Keep Jakarta Safe

    access_time11-09-2026 remove_red_eye479 personDessy Suciati
  3. Pramono Endorses Five-City Tour for Jazz Goes to Campus

    access_time12-09-2026 remove_red_eye454 personDessy Suciati
  4. No Damage Reported Following Magnitude 5.9 Seribu Islands Quake

    access_time12-09-2026 remove_red_eye446 personBudhi Firmansyah Surapati
  5. Ketapang TPS 3R Processes 13 Tons of Waste from Duri Pulo and Petojo Utara

    access_time11-09-2026 remove_red_eye429 personFolmer